Determination of erosion and sedimentation potential for sump design at the nickel mine site of PT VALE Petea Indonesia

Authors

  • Sugiarto Badaruddin Politeknik Negeri Ujung Pandang

DOI:

https://doi.org/10.31963/intek.v9i2.4187

Keywords:

Mining Site, Universal Soil Loss Equation, Sediment Delivery Ratio, Sump.

Abstract

PT. Vale Indonesia plans to mine at the Petea location using the open pit method. If viewed from the watershed boundary, the planned mining location is located in the upstream part of the Lamunto watershed. In connection with the existence of the mining plan, a solution is required to prevent things that can harm and damage the surrounding environment prior to implementation, especially related to soil erosion which is expected to impact the Lamunto watershed which is the outlet of the planned mining location. The method used in this study is to analyse the potential for erosion that occurs using the USLE (Universal Soil Loss Equation) method with the help of the ArcGIS application. Furthermore, the calculation of the sedimentation rate is carried out using the SDR (Sediment Delivery Ratio) equation based on the calculated erosion rate and the area of the mining plan that will be used to plan the sump (sediment storage tank). The results showed that the total sediment potential in sumps A, B, C, D, E, F, G, and H was 550.39 m3/year, 1195.31 m3/year, 1588.43 m3/year, 1908, 27 m3/year, 2423.33 m3/year, 1899.53 m3/year, 1941.76 m3/year, 2169.15 m3/year and 2756.29 m3/year, respectively. From these results it can be seen that the slope factor (LS) is more influential than the catchment area in calculating the sediment potential as evidenced by the total sediment potential in sump D which is greater than sump F.

References

J. S. Ahn and C.-M. Chon, “Geochemical Distributions of Heavy Metals and Cr Behavior in Natural and Cultivated Soils of Volcanic Jeju Island, Korea,†Geosystem Eng., vol. 13, no. 1, pp. 9–20, Mar. 2010, doi: 10.1080/12269328.2010.10541304.

Y. Choi, H. Yi, and H.-D. Park, “A New Algorithm for Grid-Based Hydrologic Analysis by Incorporating Stormwater Infrastructure,†Comput. Geosci., vol. 37, no. 8, pp. 1035–1044, Aug. 2011, doi: 10.1016/j.cageo.2010.07.008.

H. T. Hanh, J.-Y. Kim, S. Bang, and K.-W. Kim, “Sources and Fate of As in the Environment,†Geosystem Eng., vol. 13, no. 1, pp. 35–42, Mar. 2010, doi: 10.1080/12269328.2010.10541307.

J. Suh, Y. Choi, T.-D. Roh, H.-J. Lee, and H.-D. Park, “National-Scale Assessment of Landslide Susceptibility to Rank the Vulnerability to Failure of Rock-Cut Slopes Along Expressways in Korea,†Environ. Earth Sci., vol. 63, no. 3, pp. 619–632, Jun. 2011, doi: 10.1007/s12665-010-0729-6.

C. Sunwoo, W.-K. Song, and D.-W. Ryu, “A Case Study of Subsidence over an Abandoned Underground Limestone Mine,†Geosystem Eng., vol. 13, no. 4, pp. 147–152, Dec. 2010, doi: 10.1080/12269328.2010.10541322.

C. Teparut and S. Sthiannopkao, “Mae Moh Lignite Mine and Environmental Management,†Geosystem Eng., vol. 14, no. 2, pp. 85–94, Jun. 2011, doi: 10.1080/12269328.2011.10541335.

I. M. Muhtasar, M. Sholichin, and R. Asmaranto, “Studi Erosi Dan Sedimentasi Tambang Batubara Pada Pit Pinang South Pt. Kaltim Prima Coal Menggunakan Geographic Information System (ArcGIS),†J. Teknol. dan Rekayasa Sumber Daya Air, vol. 2, no. 1, pp. 218–230, 2022.

Subowo, “Penambangan Sistem Terbuka Ramah Lingkungan Dan Upaya Reklamasi Pasca Tambang Untuk Memperbaiki Kualitas Sumberdaya Lahan dan Hayati Tanah,†J. Sumberd. Lahan, vol. 5, no. 2, pp. 83–94, 2011.

D. H. Wafi and W. D. Ratminah, “Rencana Reklamasi Lahan Bekas Penambangan CV Jati Kencana, di Desa Karangjati, Kecamatan Bergas, Kabupaten Semarang,†in Seminar Nasional Sains dan Teknologi Terapan, 2019, pp. 507–512.

C. N. Ezugwu, “Sediment Deposition in Nigeria Reservoirs: Impacts and Control Measures,†Innov. Syst. Des. Eng., vol. 4, no. 15, pp. 54–62, 2013.

S. Sarminah, D. Kristianto, and M. Syafrudin, “Analisis Tingkat Bahaya Erosi Pada Kawasan Reklamasi Tambang Batubara PT Jembayan Muarabara Kalimantan Timur,†ULIN J. Hutan Trop., vol. 1, no. 2, pp. 154–162, Feb. 2018, doi: 10.32522/ujht.v1i2.793.

A. Ward, A. Smith, and J. Caldwell, “Surface erosion and Sediment Control at Opencast Mines in Southern Africa,†in Challenges in African Hydrology and Water Resources (Proceedings of the Harare Symposium), 1984, pp. 517–527.

V. Ferro and M. Minacapilli, “Sediment Delivery Processes at Basin Scale,†Hydrol. Sci. J., vol. 40, no. 6, pp. 703–717, Dec. 1995, doi: 10.1080/02626669509491460.

V. Ferro, “Further Remarks On A Distributed Approach to Sediment Delivery,†Hydrol. Sci. J., vol. 42, no. 5, pp. 633–647, Oct. 1997, doi: 10.1080/02626669709492063.

U. C. Kothyari and S. K. Jain, “Sediment Yield Estimation Using GIS,†Hydrol. Sci. J., vol. 42, no. 6, pp. 833–843, Dec. 1997, doi: 10.1080/02626669709492082.

V. Ferro, P. Porto, and G. Tusa, “Testing a Distributed Approach for Modelling Sediment Delivery,†Hydrol. Sci. J., vol. 43, no. 3, pp. 425–442, Jun. 1998, doi: 10.1080/02626669809492136.

B. Tribiyono, S. B. Yuwono, and I. S. Banuwa, “Estimasi Erosi dan Potensi Sedimen DAM Batutegi di DAS Sekampung Hulu Dengan Metode SDR (Sediment Delivery Ratio),†J. Hutan Trop., vol. 6, no. 2, p. 161, Sep. 2018, doi: 10.20527/jht.v6i2.5404.

C. Asdak, Hidrologi dan Pengelolaan Daerah Aliran Sungai. Yogyakarta: Gajah Mada University, 2010.

Aflizar, R. Afrizal, and T. Masunaga, “Assessment Erosion 3D Hazard with USLE and Surfer Tool: A Case Study of Sumani Watershed in West Sumatra Indonesia,†J. Trop. Soils, vol. 18, no. 1, pp. 81–92, Mar. 2013, doi: 10.5400/jts.2013.v18i1.81-92.

T. Sudarmadji and W. Hartati, “Observasi Potensi Erosi Tanah pada Lahan Revegetasi Pasca Tambang Batubara PT Multi Tambangjaya Utama (MTU) di Barito Selatan, Kalimantan Tengah,†in Prosiding Seminar Nasional Masyarakat Peneliti Kayu Indonesia (MAPEKI) XVI, 2013, pp. 290–306.

F. Isma, M. Purwandito, and Z. Ardhyan, “Estimasi Erosi dan Sedimentasi Lahan Pada DAS Langsa Berbasis Sistem Informasi Geografis (SIG),†Teras J., vol. 9, no. 1, pp. 29–41, Apr. 2019, doi: 10.29103/tj.v9i1.169.

L. Sari, J. K. Nasjono, and A. H. Rizal, “Perkiraan Sedimentasi Menggunakan Metode USLE di Bendungan Rotiklot,†J. Tek. Sipil, vol. 9, no. 1, pp. 127–140, 2020.

R. I. Siregar and I. Indrawan, “Studi Komparasi Pemodelan 1-D (Satu Dimensi) dan 2-D (Dua Dimensi) Dalam Memodelkan Banjir DAS Citarum Hulu,†Educ. Build., vol. 3, no. 2, pp. 31–37, Dec. 2017, doi: 10.24114/eb.v3i2.8255.

S.-M. Kim, Y. Choi, J. Suh, S. Oh, H.-D. Park, and S.-H. Yoon, “Estimation of Soil Erosion and Sediment Yield from Mine Tailing Dumps Using GIS: A Case Study At The Samgwang Mine, Korea,†Geosystem Eng., vol. 15, no. 1, pp. 2–9, Mar. 2012, doi: 10.1080/12269328.2012.674426.

I. W. Sutapa, “Analisis Potensi Erosi Pada Daerah Aliran Sungai (DAS) di Sulawesi Selatan,†J. SMARTek, vol. 8, no. 3, pp. 169–181, 2010.

D. Marganingrum and R. Noviardi, “Pencemaran Air dan Tanah di Kawasan Pertambangan Batubara di PT. Berau Coal, Kalimantan Timur,†J. Ris. Geol. dan Pertamb., vol. 19, no. 2, pp. 11–20, Jun. 2009, doi: 10.14203/risetgeotam2010.v20.30.

I. G. Tunas, “Pengaruh Prosedur Perkiraan Laju Erosi Terhadap Konsistensi Nisbah Pengangkutan Sedimen,†J. SMARTek, vol. 6, no. 3, pp. 135–143, 2008.

B. Ristanto, E. R. Indrayatir, and K. Nisa, “Analisa Tingkat Bahaya Erosi di DAS Asam - Asam Kabupaten Tanah Laut Dengan Sistem Informasi Geografis,†J. Sylva Sci., vol. 2, no. 4, pp. 655–666, 2019, doi: DOI: https://doi.org/10.20527/jss.v2i4.1846.

F. S. Tuhepaly, U. Andawayanti, and R. Asmaranto, “Analisa Laju Erosi dan Arahan Konservasi Lahan Berbasis ArcGIS pada DAS Parangjoho Kabupaten Wonogiri Jawa Tengah,†J. Tek. Sumber Daya Air, vol. 2, no. 1, pp. 315–327, 2022.

Downloads

Published

2023-05-01