Abstract

The aim of this research is to investigate the influence of shunt capacitor on losses of interconnection system of Sulselrabar transmission lines. In this study, DIgSILENT Power Factory 15.1 software is used to simulate the power flow in the system under study. There are three conditions applied in this study; real condition, in condition of all capacitors activated and in condition of all capacitors inactivated. Obtained results show that there are differences in the value of the losses among these three conditions, where the lowest losses is occurred at the second condition with 1,69% and the highest losses occurred at the third condition with 1,76%.

Author Biographies

Marwan Marwan, Politeknik Negeri Ujung Pandang

Jurusan Teknik Elektro

Nurhayati Nurhayati, Politeknik Negeri Ujung Pandang

Jurusan Teknik Elektro

References

Afandi, A.N.. 2005. Operasi Sistem & Pengendalian.

Malang: Dioma.

Cahyanto, Restu Dwi. 2008. Studi Perbikan Kualitas

Tegangan dan Rug – Rugi Daya Penyulang Pupur dan

Bedak Menggunakan Bank Kapasitor, Trafo Pengubah Tap

dan Penggantian Kabel Penyulang. Laporan Tugas Akhir.

Depok. Departemen Teknik Elektro Fakultas Teknik

Universitas Indonesia.

DIgSILENT Power Factory 15.1. (User Manual).

Djiteng, Marsudi. 2006. Operasi Sistem Tenaga Listrik.

Jakarta: Graha Ilmu.

PLN. 2009. Buku Petunjuk Operasi dan Pemeliharaan

Peralatan Penyaluran Tenaga Listrik. Jakarta: PT. PLN

(Persero).

Priyadi, Ardyono dkk. 2012. Analisis Stabilitas

Transient Pada Sistem Tenaga Listrik dengan

Mempertimbangkan Beban Non – Linier. Jurnal.

Surabaya. Jurusan Teknik Elektro Fakultas Teknologi

Industri Institut Teknologi Sepuluh Nopember (ITS).

RUPTL. 2014. Rencana Usaha Penyediaan Tenaga

Listrik (RUPTL) Tahun 2015 – 2024. Jakarta: PT.PLN

(Persero).

Stevenson, William D, Jr. 1996. Analisis Sistem Tenaga

Listrik. Diterjemahkan oleh Kamal Idris. Bandung. PT.

Philips Ralin Electronics.

Wikarsa, Mohamad Tresna. 2010. Studi Analisis

Program Percepatan 10.000 MW Tahap 1 pada Operasi

Sistem Tenaga Listrik Jawa Bali. Jurnal. Depok.

Departemen Teknik Elektro Fakultas Teknik Universitas

Published

2016-04-01

Issue

Section

ARTICLES